• Course Construction Report

  • Over the past few months we have put new pipes in the river right of the bridge on the fourth.  We will be seeding all that area and should be back in play for early summer . It was an area that was very unfair and unsightly so this will help with general play overall.
     
    We have new drains put in on the 6th which will help the area drain quicker and it may need more new drains down the road.  

    We have put in new mounding at the back of the 7th green and we have planted maram grass on it.  Over time this will fill in and give a nice back drop to the green.

    The ladies 8th tee box has been reshaped.  We have given it an elevated back tier with a new path coming in from the front of the men's tee box. We will be re-sodding it this week and should be in play by mid May weather permitting.

    JJ Corduff